How do you calculate loaded labor cost for restoration technicians?

The short answer

Start with the technician's wage for paid hours, then add employer-side costs: employer taxes, workers' compensation, health and other benefits, paid time off, training, uniforms and protective equipment, and tool or phone allowances. Divide the annual total by the hours the tech actually works on jobs, not hours paid, to get a loaded cost per productive hour.

Why loaded labor cost matters

Most restoration owners know what they pay a technician per hour. Far fewer know what that hour actually costs the company. The gap matters because job budgets, bids and profit reviews built on the base wage will always look better than reality. A job that seems profitable on base wage can lose money once workers' comp, benefits, training time and non-billable hours are counted.

Loaded labor cost is the number you should multiply hours by when you budget a job, review its profitability or decide whether overtime is worth it. Your accountant can help you pin down the exact components and how they apply to your business; the method below gives you the structure.

The components

Add up these costs for each technician, or for each role if techs are paid similarly, over a year:

  • Wages for all paid hours, including overtime premiums.
  • Employer taxes on wages. Your accountant or bookkeeper can give you the actual figures.
  • Workers' compensation, which for restoration work can be significant and varies by classification.
  • Health insurance and other benefits the company pays.
  • Paid time off: holidays, vacation and sick days are paid but not worked.
  • Training time and costs: course fees and the hours spent in class.
  • Protective equipment, uniforms and boots issued to the tech.
  • Phone, tablet and tool allowances.
  • Vehicle costs, if a company truck is assigned to the tech, can be included here or tracked as job overhead. Pick one approach and stay consistent.

This is the step most people miss. A tech may be paid for about 2,080 hours a year at full time, plus overtime. But not all of those are hours on jobs. Subtract:

  • Paid time off and holidays
  • Training days
  • Shop time: loading trucks, cleaning equipment, maintenance
  • Unassigned time in slow weeks
  • Drive time that is not charged to a job, depending on how you track it

The result is productive hours. Divide the total annual cost by productive hours, not paid hours, to get the loaded cost per productive hour.

A worked example

Say a technician is paid for 2,080 regular hours a year plus about 150 hours of overtime. The owner gathers annual costs from the books and expresses them as hours of base wage to keep the example simple.

ItemAnnual cost, in hours of base wage
Regular wages2,080
Overtime at time and a half (150 hours)225
Employer taxesabout 180
Workers' compensationabout 230
Health and other benefitsabout 300
Training, protective equipment, uniforms, phoneabout 100
Total annual costabout 3,115 hours of base wage

Now productive hours. Of the 2,230 hours paid (2,080 regular plus 150 overtime), the tech spent 80 hours on paid time off and holidays, 40 in training, 200 on shop time and about 110 unassigned during slow weeks. Productive hours: about 1,800.

Loaded cost per productive hour is about 3,115 divided by 1,800, or roughly 1.7 times the base wage. If you have been budgeting jobs at base wage, every labor line has been understated by a wide margin.

Use your own numbers. The multiplier for your shop could be higher or lower depending on benefits, workers' comp classification and how much non-billable time your techs carry.

How to use the number

  1. Budget jobs with it. Multiply estimated crew hours by loaded cost, not base wage.
  2. Review job profitability with it. Actual hours times loaded cost shows the true labor cost of a closed job.
  3. Evaluate overtime. Overtime raises the cost of an hour; know by how much before approving routine overtime outside storm weeks.
  4. Recalculate at least yearly, and when wages, benefits or insurance change.
  5. Watch productive hours. Improving scheduling and reducing shop time lowers loaded cost without touching wages.

Roles and blended rates

Many shops calculate a separate loaded rate for crew leads, technicians and helpers, then use a blended crew rate for budgeting. For example, a crew of one lead and two techs gets a blended rate by adding the three loaded rates and dividing by three. That keeps estimates simple while still reflecting who is actually on the job. When crews change makeup often, budget by role instead and let the time records show who worked.

Common mistakes

  • Dividing by paid hours. It hides the cost of non-billable time and makes every job look cheaper.
  • Leaving out workers' comp. In restoration it is often one of the largest add-ons.
  • Using one number for every role. Crew leads, techs and helpers can have very different loaded costs.
  • Never updating it. Insurance renewals and wage changes shift the number every year.
  • Treating it as a tax calculation. This is a management number. Your accountant handles the tax side.

How RestoreUnited can help

RestoreUnited's Time Tracking captures hours against jobs, which gives you the productive-hours side of the calculation, and Job Budgeting lets you plan labor by job using your loaded rate. QuickBooks Integration helps keep job data aligned with your books, so the cost inputs and job hours come from the same place.

See it in RestoreUnited: Time Tracking

RestoreUnited product video

Frequently asked questions

What is the difference between loaded and base labor cost?

Base cost is the hourly wage. Loaded cost adds employer taxes, workers' compensation, benefits, paid time off, training and equipment, then divides by productive hours. It reflects what an hour on a job actually costs the company.

Should drive time be included in productive hours?

It depends on how you track and charge it. If drive time is assigned to jobs, count it as productive. If it is not charged to any job, treat it as non-productive. Pick one method and use it consistently.

How often should we recalculate loaded labor cost?

At least once a year and whenever wages, benefits, insurance or workers' comp rates change. Ask your accountant to help confirm the employer cost inputs.